Nhon Trach Gas-fired Power Company: Generate combined cycle in March 2009 Nhon Trach Gas-fired Power Company: Generate combined cycle in March 2009
(7/30/2008 2:55:49 PM)
As revealed by the Project Management Board of Nhon Trach Gas-fired Power Company, on July 23, engineers, experts and suppliers successfully fired the gas turbine unit No.2.
(7/30/2008 2:55:49 PM)
 INVESTMENT
Investment
Buon Kuop Hydropower: Boost progress arte to complete tunnel No.1 Buon Kuop Hydropower: Boost progress arte to complete tunnel No.1
(9/23/2008)
To date, the construction of the main dam of Buon Kuop hydropower project has been basically completed, in which the job of damming up has been 99.4% finished and has reached the height for flood prevention. However, there has been still 8,300 m3 of rock and soil remaining. The main cause is the continuously heavy rain. At present, contractors are making use of the weather condition to complete the job of damming up in October 2008.
(9/23/2008)
 PRODUCTION
Production
Still cut off power in peak hours Still cut off power in peak hours
(9/29/2008)
Up to September, the shortage of electricity in peak hours has not been improved and this situation is expected to last to October. Therefore, 11 power plants of The Electricity of Vietnam (EVN) still have to set up the schedule of power cut in localities.
(9/29/2008)
 BUSINESS
Business
Pay electricity tariff through ACB Pay electricity tariff through ACB
(9/29/2008)
Asian Bank (ACB) has just implemented the service to collect electricity tariffs for Ho Chi Minh City Power Company in more than 100 branches and trading offices in the City. Accordingly, all customers of Ho Chi Minh City Power Company will be able to pay their electricity tariffs through ACB for free of charge with the following methods:
(9/29/2008)
 INNOVATION
Innovation
EVN Telecom: Proposes to chose strategic partner before IPO EVN Telecom: Proposes to chose strategic partner before IPO
(6/9/2008)
As revealed by The Electricity of Vietnam (EVN), regardless of the downward trend in the stock market, EVN Telecom still carries out equitization in 2008.
(6/9/2008)
  KeyWord  
 News
Still cut off power in peak hours Still cut off power in peak hours
(9/29/2008)
Up to September, the shortage of electricity in peak hours has not been improved and this situation is expected to last to October. Therefore, 11 power plants of The Electricity of Vietnam (EVN) still have to set up the schedule of power cut in localities.
(9/29/2008)
Pay electricity tariff through ACB Pay electricity tariff through ACB
(9/29/2008)
Asian Bank (ACB) has just implemented the service to collect electricity tariffs for Ho Chi Minh City Power Company in more than 100 branches and trading offices in the City. Accordingly, all customers of Ho Chi Minh City Power Company will be able to pay their electricity tariffs through ACB for free of charge with the following methods:
(9/29/2008)
Speed up progress rate of power plants in the South Speed up progress rate of power plants in the South
(9/26/2008)
In the afternoon of September 25, Deputy Prime Minister Hoang Trung Hai accompanied by the Government Working Group paid a visit to Nhon Trach Gas Power Project in Dong Nai province, directly examining the progress rate of Nhon Trach Power Company 1 and supplying concrete guidance for investors and contractors about the implementation of power plants in Nhon Trach and Ca Mau.
(9/26/2008)
Buon Kuop Hydropower: Boost progress arte to complete tunnel No.1 Buon Kuop Hydropower: Boost progress arte to complete tunnel No.1
(9/23/2008)
To date, the construction of the main dam of Buon Kuop hydropower project has been basically completed, in which the job of damming up has been 99.4% finished and has reached the height for flood prevention. However, there has been still 8,300 m3 of rock and soil remaining. The main cause is the continuously heavy rain. At present, contractors are making use of the weather condition to complete the job of damming up in October 2008.
(9/23/2008)
EVN: Directly sell electricity to rural households EVN: Directly sell electricity to rural households
(9/19/2008)
The Electricity of Vietnam (EVN) is preparing to accept the low-voltage power network so as to directly sell electricity to households in rural areas.
(9/19/2008)
Uong Bi Thermopower Company Extension: Temporarily stops operating Uong Bi Thermopower Company Extension: Temporarily stops operating
(9/18/2008)
According to the National Acceptance Commission of Construction Project, Uong Bi Thermopower Company Extension is expected to stop operating from now to the end of December, 2008 in order to overcome the lightning-stricken incident of the 220 kV Uong Bi – Trang Bach power line, which has ruined the insulator of the high-voltage line in the 220 kV transformer substation of the plant. 
(9/18/2008)
Ho Chi Minh City: Boosts the promotion campaign for power-saving devices Ho Chi Minh City: Boosts the promotion campaign for power-saving devices
(9/15/2008)
In accordance with the promotion campaign of power-saving devices, for the first 7 months of the year 2008, Ho Chi Minh City Power Company has promoted and sold 52,015 compact lights, accounting for 43.35% of the 2008 year plan.
(9/15/2008)
Speed up the progress rate of power projects Speed up the progress rate of power projects
(9/15/2008)
In the event that the progress rate of power projects is still falling behind the schedule, Deputy Prime Minister Hoang Trung Hai, at the end of last week, chaired the meeting of the Management Board of Power Plan VI.
(9/15/2008)
Interbranch working group on BOT, BTO and BT power generation projects established Interbranch working group on BOT, BTO and BT power generation projects established
(9/15/2008)
The Ministry of Industry and Trade has just established an Interbranch Working Group on BOT, BTO and BT power generation projects.
(9/15/2008)
Close the waste outlet No.1 of Hoa Binh reservoir Close the waste outlet No.1 of Hoa Binh reservoir
(9/12/2008)
As guided by the Government, the Flood and Storm Prevention Central Management Board has released the document No. 36/CĐ-TW about closing the waste outlet No.1.
(9/12/2008)
 USEFUL INFORMATION
 PROCUREMENTS
Procurements
Miscellaneous insulators Miscellaneous insulators
(3/18/2008)

Package 2: Miscellaneous insulators

(3/18/2008)
Low-voltage copper cable Low-voltage copper cable
(3/18/2008)

Package: Low-voltage copper cable

(3/18/2008)
 RECRUITMENT
Recruitment
Information Technology Center seeks recruitment Information Technology Center seeks recruitment
(10/5/2007)

EVN’s Information Technology Center is a member of the Electricity of Vietnam Group (EVN) functioning as a center of researching and developing IT projects on power industry comprising of  ERP software system, electric Information System of Customer Management, Power Plant Management, Customer Management system and telecom’s tariff accounting system, software systems used for financial companies, banks, etc. Some vacancies are required to meet our business demand:

(10/5/2007)
Information Technology Center seeks recruitment Information Technology Center seeks recruitment
(9/26/2007)

EVN’s Information Technology Center is a member of the Electricity of Vietnam Group (EVN) functioning as a center of researching and developing IT projects on power industry comprising of  ERP software system, electric Information System of Customer Management, Power Plant Management, Customer Management system and telecom’s tariff accounting system, software systems used for financial companies, banks, etc. Some vacancies are required to meet our business demand:

(9/26/2007)
  NEWS
News
Speed up progress rate of power plants in the South Speed up progress rate of power plants in the South
(9/26/2008)
In the afternoon of September 25, Deputy Prime Minister Hoang Trung Hai accompanied by the Government Working Group paid a visit to Nhon Trach Gas Power Project in Dong Nai province, directly examining the progress rate of Nhon Trach Power Company 1 and supplying concrete guidance for investors and contractors about the implementation of power plants in Nhon Trach and Ca Mau.